Road Construction Schedule for the Week of 9/3-9/9

Road Construction Schedule for the Week of 9/3-9/9

BINGHAMTON, NY – The Highway Division of the Broome County Public Works Department in conjunction with the New York State Department of Transportation has announced the following roads scheduled to be rehabbed during the week of September 3rd through September 9th.

 Kiebel Road will be paved on September 9th.

Grader Patch on Tunnel, Quaker Lake Roads and Upper Pennsylvania Ave.

Sweeping on roads that have received Oil & Stone including Nowlan, Stratmill, Stateline, Edson and Nanticoke Roads.

The mowing along the edge of various county roads will also be occurring this week. There is no set schedule but the impact to traffic should be minimal.

All projects are dependent on weather.